On 15 December 2023 the Electricity Authority approved a settlement between Counties Energy Limited and Awhitu Windfarms Limited.

The settlement was an outcome of an investigation of Counties Energy Limited for alleged breaches of the Electricity Industry Participation Code 2010 (the Code).

Awhitu Windfarms Limited reported to the Electricity Authority that Counties Energy Limited may have breached clause 23(2) of Schedule 6.1 of the Code on 7 June 2020.

As a result of the Electricity Authority’s approval, the settlement is final and binding on all parties (subject to regulation 26 of the Electricity Industry (Enforcement) Regulations 2010).

The Electricity Authority informed the parties of its settlement decision on 21 December 2023.

View the settlement agreement

Related News

Electricity Authority releases updated improved billing guidance

The Electricity Authority Te Mana Hiko has published updated guidance to help power companies implement important billing reforms by 1 April 2027. The new rule…

Code changes to address common quality issues

A package of targeted common quality Code amendments has been made by the Electricity Authority Te Mana Hiko to help maintain the security and resilience of th…

Authority discontinues alleged Code breaches at Waipipi Wind Farm

The Electricity Authority has decided to discontinue its investigations into alleged breaches of the Electricity Industry Participation Code by Genesis Energy …

Subscribe to Market Brief

Get the latest news, updates and market insights from the Electricity Authority direct to your inbox.