General news
Case study: Meeting payment deadlines for cleared funds
- Code
- Compliance
We’ve published a case study on participants’ obligations to meet payment deadlines with the reconciliation manager and keep the participant register up to date.
Case study: Meeting payment deadlines for cleared funds
The case study looks at the circumstances of a participant’s late payment to the clearing manager and subsequent failed attempts to contact them that constituted a breach of clause 14.34 of the Electricity Industry Participation Code 2010 and Section 29 (2) of the Electricity Industry Act 2010.
It is vital that participants remain on top of their obligations, have a strong compliance framework in place with well-established processes and controls and allocated roles and responsibilities.
The case is a reminder for all participants to keep their contact details up to date in the Participant register so that the Authority can communicate with organisation's most current contacts.
Related News
New rules to improve application processes for network connections: technical consultation opens
We are inviting feedback on the draft Code for recently announced new rules that make it easier and faster to connect to the electricity network, or to upgrade…
Connection pricing methodologies Code amendment finalised and FAQs published
We’ve published a new webpage of frequently asked questions for the new rules to improve connection pricing methodologies. These FAQs are designed to help dist…
Decision on causer of 26 July 2024 under-frequency event
Following consultation, we have determined that Transpower New Zealand Limited, as grid owner, is the causer of the 26 July 2024 under-frequency event.