Case study: Meeting payment deadlines for cleared funds
- Code
- Compliance
We’ve published a case study on participants’ obligations to meet payment deadlines with the reconciliation manager and keep the participant register up to date.
Case study: Meeting payment deadlines for cleared funds
The case study looks at the circumstances of a participant’s late payment to the clearing manager and subsequent failed attempts to contact them that constituted a breach of clause 14.34 of the Electricity Industry Participation Code 2010 and Section 29 (2) of the Electricity Industry Act 2010.
It is vital that participants remain on top of their obligations, have a strong compliance framework in place with well-established processes and controls and allocated roles and responsibilities.
The case is a reminder for all participants to keep their contact details up to date in the Participant register so that the Authority can communicate with organisation's most current contacts.
Related News
Seeking feedback on 17 September 2024 under-frequency event
We are seeking feedback from generators, the grid owner and other market participants who may be substantially affected by an under-frequency event on 17 Septe…
Rulings Panel decision on security constraint Code breach
The Rulings Panel has ordered Transpower to pay a fine of $65,000 after finding it breached the Electricity Industry Participation Code 2010 in relation to the…
Cross-submissions open on our connection pricing and processes proposals
Submissions on the proposed rule changes for distribution connection pricing and the application processes to connect are now available on the Authority websit…