General news

Decision on 11 April 2024 under-frequency event

  • Generation
  • Compliance

The Electricity Authority Te Mana Hiko's final determination is that Genesis Energy Limited, as the generator that owns Huntly Unit 4, was the causer of the 11 April 2024 under-frequency event (UFE).

The Authority's reasons for this final determination are:

  • A UFE occurred at 12.25am on 11 April 2024 when frequency dropped to 49.17Hz in the North Island and 49.25Hz in the South Island
  • The interruption/reduction of electricity occurred at the grid injection point for Huntly Unit 4, which belongs to Genesis
  • No other asset was identified as having caused or potentially caused the UFE
  • Genesis agreed with the system operator’s assessment that Genesis was the causer of the UFE
  • The Authority did not receive any feedback that disputed its draft determination.

In accordance with clause 8.65 of the Electricity Industry Participant Code, the clearing manager will rebate the event charges to the relevant participants. The event charge calculated in the system operator’s report to the Authority is $205,003.75.

Any dispute of this final determination can be lodged with the Rulings Panel via registrar@electricityrulingspanel.nz by 5pm, 17 December 2024.

About 11 April 2024 under-frequency event

Related News

Electricity Authority lodges formal complaint over alleged Code breach

The Electricity Authority Te Mana Hiko has lodged a formal complaint with the Rulings Panel alleging a breach of the Electricity Industry Participation Code 20…

Exemptions from the Code for 2025

This year, the Electricity Authority Te Mana Hiko approved 11 exemptions and three exemption amendments from obligations in the Electricity Industry Particip…

Seeking feedback on 11 July 2025 under-frequency event

The Electricity Authority Te Mana Hiko is seeking feedback from participants who may be substantially affected by the under-frequency event of 11 July 2025.