Decision on 11 April 2024 under-frequency event

  • Generation
  • Compliance

The Electricity Authority Te Mana Hiko's final determination is that Genesis Energy Limited, as the generator that owns Huntly Unit 4, was the causer of the 11 April 2024 under-frequency event (UFE).

The Authority's reasons for this final determination are:

  • A UFE occurred at 12.25am on 11 April 2024 when frequency dropped to 49.17Hz in the North Island and 49.25Hz in the South Island
  • The interruption/reduction of electricity occurred at the grid injection point for Huntly Unit 4, which belongs to Genesis
  • No other asset was identified as having caused or potentially caused the UFE
  • Genesis agreed with the system operator’s assessment that Genesis was the causer of the UFE
  • The Authority did not receive any feedback that disputed its draft determination.

In accordance with clause 8.65 of the Electricity Industry Participant Code, the clearing manager will rebate the event charges to the relevant participants. The event charge calculated in the system operator’s report to the Authority is $205,003.75.

Any dispute of this final determination can be lodged with the Rulings Panel via registrar@electricityrulingspanel.nz by 5pm, 17 December 2024.

About 11 April 2024 under-frequency event

Related News

First compliance reports for retailers under Consumer Care Obligations due 30 September

The Electricity Authority is notifying electricity retailers that their 2024/25 compliance reports for the Consumer Care Obligations are now available to compl…

Centralised wind and solar forecaster contract awarded

The Electricity Authority has awarded a contract to provide centralised wind and solar forecasting services to DNV Services.

Seeking feedback on 21 December 2024 under-frequency event

We are seeking feedback from generators, the grid owner and other market participants who may have been substantially affected by the under-frequency event of …