Open networks
Integration of hosting capacity into Part 6 of the Code, sunset clause
Upcoming
Open
Closed
Decision
View submissions
Submissions closed 1 September 2020
Share
Consultation
From 18 August to 1 September 2020, we consulted on a further amendment to Part 6 of the Electricity Industry Participation Code (Code). Having considered submissions on the October 2019 consultation, we proposed a 5-year time period to end date the relevant clauses related to power quality modes and the maximum export power should be included. This would incentivise local distributors and other industry parties to develop innovative new approaches to managing network congestion and enhancing hosting capacity.
On 27 July 2021, we published our decision to amend the Code effective from 1 September 2021 to 1 September 2026.
Submissions
-
EEA4 pages
-
Orion2 pages
-
Unison2 pages
-
Vector5 pages
-
Wellington Electricity2 pages