Under-frequency event determinations
27 June 2024 under-frequency event
Upcoming
Open
Closed
Decision
Submissions closed 15 November 2024
Share
Consultation
At 12:32pm on 27 June 2024 an under-frequency event occurred when 236.44MW of generation injection was interrupted or lost at the Huntly grid connection point. This resulted in a drop in frequency of 49.21Hz in the North Island and 49.25Hz in the South Island.
This consultation sought feedback from interested parties on the Electricity Authority’s draft determination that Genesis, as the generator which owns Huntly Unit 1, was the causer of the under-frequency event on 27 June 2024.
The Authority would like to thank those who make a submission. Feedback will be considered and then we will make a final determination on the causer.